When setting up for a cable pull in a tray between floors, which action should be performed from the higher floor?

Prepare for the Electrical Job Information 1 Test. Study with detailed multiple choice questions; each comes with hints and explanations. Enhance your exam readiness with focused content to boost your scores!

When setting up for a cable pull in a tray between floors, feeding the cable from the higher floor is the correct action. This is necessary because it allows for a more controlled and manageable process. By feeding the cable downwards, you can ensure that it is aligned properly and reduces the risk of kinks or snags that could occur if you were pulling it up from below.

The weight of the cable also plays a role; when fed downward, gravity assists in managing the load, which simplifies the overall process. Additionally, it allows personnel on the higher floor to observe the pull and make adjustments as needed while minimizing the need for movements between levels.

Other actions, such as pulling, inspecting, or disconnecting, do not offer the same benefits during the initial setup for a cable pull in this specific scenario. Pulling would generally take place after the cable is fed, inspecting can be done at various stages but is not the initial setup task, and disconnecting is completely unrelated to the process of setting up for a successful cable pull.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy